One of the projects that was completed and inaugurated was the Liso project in Dillo district of Borana state. The project has the capacity to store 3 million cubic meters of water and will develop 103 hectares of land for the benefit of 200 households.
The height of the dam is 9M and the length is 710m. The project was kna conducted by the construction company Golden Construction Works and the Oromia Engineering Corporation served as the consultant.